How to do Powder Coating ?

In Powder coating process, CRCA surface is given Anti Corrosive Surface treatment, then Epoxy Powder is applied, melted and hardened.

Time needed: 3 hours

How to do Powder Coating ?

  1. Degrease

    Oil or Grease is removed by diping CRCA Steel fabrication into Acidic /Alkaline solution at Ambient temperature for 30 minutes.
    Immersion Solution : Acidic/Alkaline Solution.
    Temperature : Ambient/Room Temperature.
    Duration : 30 minutes.

  2. Rinse – I

    CRCA Steel Fabrication is Rinsed, so that no Oil/Grease/Acidic solution is transfected to next stage.
    Immersion Solution : Water
    Temperature : Ambient/Room Temperature.
    Duration : 10 minutes.

  3. Chemical Cleaning  / Derusting

    CRCA Steel Fabrication is dipped into Hydrocloric Acid, which removes Rust and Mil Scales on the Steel Fabrication. Hydrocloric Acid is kept at Ambient temperature.  
    Immersion Solution : Hydrocloric Acid
    Temperature : Ambient/Room Temperature.
    Duration : 30 minutes.

  4. Rinse – II

    CRCA Steel Fabrication is Rinsed, so that no Rust/Hydrocloric Acid is transfected to next stage.
    Immersion Solution : Water
    Temperature : Ambient/Room Temperature.
    Duration : 10 minutes.

  5. Surface Activation

    CRCA Steel Fabrication is dipped into Activation chemicals.
    Immersion Solution : Activation Chemical Solution.
    Temperature : Ambient/Room Temperature.
    Duration : 5 minutes.

  6. Phosphating

    CRCA Steel Fabrication is dipped into solution of Zinc Phosphate at Ambient Temperature. 
    Immersion Solution : Zinc Phosphate.
    Temperature : Ambient/Room Temperature.
    Duration : 30 minutes.

  7. Rinse – III

    CRCA Steel Fabrication is Rinsed.
    Immersion Solution : Water
    Temperature : Ambient/Room Temperature.
    Duration : 10 minutes.

  8. Passivation

    CRCA Steel Fabrication is dipped into Decxylite Solution at Ambient Temperature to seal the surface for obtaining maximum corrosion resistance.
    Immersion Solution : Decxylite Solution
    Temperature : Ambient/Room Temperature.
    Duration : 5 minutes.

  9. Oven Drying

    CRCA Steel Fabrication is Dryed by Hot Air at 150 *C.
    Environment : Hot Air
    Temperature : 150 *C Temperature.
    Duration : 10 minutes.

  10. Powder Coating

    CRCA Steel Fabrication is powder coated by Spraying the Epoxy powder of desired color.
    Environment : Spray of Epoxy Powder
    Temperature : 150 *C Temperature.
    Duration : 15 minutes.

  11. Curing / Baking

    CRCA Steel Fabrication is Baked in Electric Oven at 150 *C for 15 minutes.
    Environment : Oven
    Temperature : 150 *C Temperature.
    Duration : 15 minutes.

Related Articles:

    Degree of Burn

    Degree of Burn is the level of depth of Burn effect on the human skin up to bones.

    What is Electrical Insulating Materials ?

    Nonconducting material that provides electric isolation of two parts at different voltages.
    It must have an electrical resistivity and a dielectric strength sufficiently high for the given application.
    The secondary requirements relate to thermal and mechanical properties.

    What is I2t – Let through Energy ?

    I2t – Let through Energy is available thermal energy resulting from Current Flow during circuit opening in Fuse, MCCB, MCB.Unit is A2S (Ampere2 Second)

    Burns caused by Arc Flash

    Degree of severity of burns is based on size and depth of the burn on human body. Fire, steam, Radiation, chemicals, Electric Arc, can cause burns.